Clave | Descripción del Análisis de Precio Unitario | Unidad |
2068-15 | DESCARGAS DE TUBERIA DE ACERO DE 4″ x 30.00 M DE DIAMETRO CED-80 SIN COSTURA INCLUYE INSTALACION DE VALVULA CHECK, VALVULA DE COMPUERTA, SOPORTES PARA TUBERIA, CORTE, SOLDADURA, PINTURA ANTICORROSIVA, PINTURA EPOXICA Y CONEXION A MANIFUL DE SALIDA | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TUBO ACERO 4″ 1 | TUBO DE ACERO CED-80 DE 4″ DE DIAMETRO SIN COSTURA | M | 30.000000 | $546.48 | $16,394.40 |
VAL COMPUERTA 4″ 1 | VALVULA DE COMPUERTA DE 4″ DE DIAMETRO | PZA | 1.000000 | $3,044.00 | $3,044.00 |
VAL CHECK 4″ 1 | VALVULA CHECK DE 4″ DE DIAMETRO | PZA | 1.000000 | $5,405.00 | $5,405.00 |
MANOMETRO PRESION 1 | MANOMETRO DE PRESION | PZA | 1.000000 | $280.00 | $280.00 |
BRIDA ACERO 4″ 1 | BRIDA DE ACERO DE 4″ DE DIAMETRO PARA 125 LBS | PZA | 4.000000 | $340.00 | $1,360.00 |
EMPAQUE NEOP 4″ 1 | EMPAQUE DE NEOPRENO ROJO DE 3/16″ x 4″ | PZA | 4.000000 | $45.00 | $180.00 |
VAL DE BOLA 1/2″ 1 | VALVULA DE BOLA DE 1/2″ DE DIAMETRO | PZA | 1.000000 | $125.00 | $125.00 |
NIPLE ACERO 1/2″ 1 | NIPLE DE ACERO GALVANIZADO DE 1/2″ | PZA | 1.000000 | $4.44 | $4.44 |
COPLE GALV 1/2″ 1 | COPLE DE ACERO GALVANIZADO DE 1/2″ | PZA | 1.000000 | $5.84 | $5.84 |
SOLDADURA E-7018 1 | SOLDADURA E-7018 | KG | 30.000000 | $49.88 | $1,496.40 |
OXIGENO 1 | OXIGENO | M3 | 2.500000 | $39.00 | $97.50 |
ACETILENO 1 | ACETILENO | KG | 1.250000 | $130.00 | $162.50 |
PINTURA EPOXICA 1 | PRIMARIO EPOXICO RP-6 | LTO | 4.000000 | $85.00 | $340.00 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 4.000000 | $90.00 | $360.00 |
TOR HEX 5/8″X3 1/2″ | TORNILLO HEXAGONAL INOXIDABLE DE 5/8″ x 3 1/2″ | PZA | 16.000000 | $28.00 | $448.00 |
ANGULO 1/4″X2″X2″ 1 | ANGULO DE 2″ x 2″ x 1/4″ | KG | 10.000000 | $20.00 | $200.00 |
CODO GALV 45´X4″ 1 | CODO DE ACERO GALVANIZADO DE 45´x 4″ | PZA | 3.000000 | $416.93 | $1,250.79 |
CODO GALV 90´X4″ 1 | CODO DE ACERO GALVANIZADO DE 90´x 4″ | PZA | 5.000000 | $476.46 | $2,382.30 |
THINER 1 | THINER PARA PINTURA EPOXIMASTIC | LTO | 2.000000 | $40.00 | $80.00 |
MAS DESECHABLES 1 | MASCARILLA DESECHABLES | PZA | 1.000000 | $11.30 | $11.30 |
CAP ALG PINTAR 1 | CAPUCHA DE ALGODON PARA PINTAR (SPRAY SOCK) | PZA | 1.000000 | $34.00 | $34.00 |
LENTES DE SEG 1 | LENTE DE SEGURIDAD | PZA | 1.000000 | $46.80 | $46.80 |
LIJA GRUESA 1 | LIJA GRUESA | PZA | 4.000000 | $11.00 | $44.00 |
ESTOPA 2A 1 | ESTOPA SEGUNDA | KG | 1.000000 | $52.00 | $52.00 |
PLACA DE ACERO 1/2″1 | PLACA DE ACERO DE 1/2″ | KG | 16.000000 | $12.50 | $200.00 |
Suma de Material | $34,004.27 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.200000 | $307.31 | $61.46 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 2.000000 | $251.32 | $502.64 |
AYUDANTE OP ESP 1 | AYUDANTE OPERARIO ESPECIALISTA | JOR | 2.000000 | $195.39 | $390.78 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 2.000000 | $197.97 | $395.94 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 4.000000 | $185.16 | $740.64 |
Suma de Mano de Obra | $2,091.46 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $2,091.46 | $62.74 |
Suma de Herramienta | $62.74 | ||||
Equipo | |||||
EQ SANDBLAST 1 | EQUIPO PARA SANDBAST CON ACCESORIOS | HORA | 4.000000 | $16.28 | $65.12 |
COMPRESOR AIRE 250 2 | COMPRESOR DE AIRE INGERSOLL RAND DE 250 PCM MOTOR DIESEL 105 HP | HORA | 4.000000 | $163.21 | $652.84 |
PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 16.000000 | $113.61 | $1,817.76 |
EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 16.000000 | $26.43 | $422.88 |
CAMION PLATAF 6.8T 1 | CAMION PLATAFORMA FORD DE 6.8 TON DE CAPACIDAD | HORA | 2.000000 | $241.47 | $482.94 |
Suma de Equipo | $3,441.54 | ||||
Costo Directo | $39,600.01 |