Clave | Descripción del Análisis de Precio Unitario | Unidad |
PV13-01 | GUARNICION TIPO PECHO PALOMA CON CONCRETO PREMEZCLADO F’c=150 KG/CM2 CON MATERIALES DE LA REGION INCLUYE PASAJUNTAS @ 3.0 M EXCAVACION Y/O RELLENO COMPACTADO, CIMBRA Y DESCIMBRA Y LIMPIEZA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.550000 | $16.15 | $8.88 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.080000 | $34.00 | $2.72 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
CELOTEX 13MM 1 | CELOTEX 13 MM DE ESPESOR | M2 | 0.015000 | $31.00 | $0.47 |
CONC PREM 150 1 | CONCRETO PREMEZCLADO F’c=150 KG/CM2 | M3 | 0.095000 | $1,039.28 | $98.73 |
CURACRETO 1 | CURACRETO | LTO | 0.250000 | $18.00 | $4.50 |
Suma de Material | $122.84 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003000 | $307.31 | $0.92 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.030000 | $251.32 | $7.54 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.030000 | $197.97 | $5.94 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.030000 | $185.16 | $5.55 |
Suma de Mano de Obra | $19.95 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $19.95 | $0.60 |
Suma de Herramienta | $0.60 | ||||
Equipo | |||||
VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE | HORA | 0.100000 | $42.87 | $4.29 |
Suma de Equipo | $4.29 | ||||
Costo Directo | $147.68 |