Clave | Descripción del Análisis de Precio Unitario | Unidad |
4080-03 | CIMBRA DE MADERA PARA ACABADO COMUN EN CONTRATRABES | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 6.000000 | $16.15 | $96.90 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.150000 | $34.00 | $5.10 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.190000 | $19.00 | $3.61 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 0.730000 | $2.50 | $1.83 |
Suma de Material | $113.08 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.009260 | $307.31 | $2.85 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.092590 | $251.32 | $23.27 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.092590 | $197.97 | $18.33 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.046300 | $185.16 | $8.57 |
Suma de Mano de Obra | $53.02 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $53.02 | $1.59 |
Suma de Herramienta | $1.59 | ||||
Equipo | |||||
CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.014810 | $202.91 | $3.01 |
Suma de Equipo | $3.01 | ||||
Costo Directo | $170.70 |