| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ACA-19 | SUMINISTRO Y COLOCACION DE MURO DE TABLAROCA 2 CARAS EN CAJAS DE SEGURIDAD, INCLUYE: PASTA, PINTURA, MATERIAL, MANO DE OBRA HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DUROCK-003 | POSTE METALICO USG 9.20 * 3.05 CAL 22 | ML | 2.750000 | $15.63 | $42.98 |
| DUROCK-006 | CANAL 6.35 CAL. 22 | ML | 0.880000 | $16.00 | $14.08 |
| DUROCK-005 | TORNILLO PARA DUROCK DE 1 1/4" | PZA | 25.000000 | $0.36 | $9.00 |
| DUROCK-007 | TORNILLO METAL METAL | PZA | 15.000000 | $0.60 | $9.00 |
| TABLARROCA 14 | FULMIMNANTEDX-72 | PZA | 3.333333 | $1.50 | $5.00 |
| TABLARROCA 18 | ANCLA HILTI DX-72 | PZA | 3.333333 | $1.90 | $6.33 |
| TABLARROCA-14 | Panel de tablarroca de 13 mm ( 1.22 * 2.44 mts. ) den glass | hoja | 0.800000 | $130.00 | $104.00 |
| TABLARROCA-06 | Perfacinta refuerzo para juntas rollo de 75.00 ml. | rollo | 0.053333 | $21.46 | $1.14 |
| TABLARROCA-07 | Compuesto redimix p/juntas caja de 25 kg | caja | 0.080000 | $114.14 | $9.13 |
| Suma de Material | $200.67 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 97 | (1 Of.Tablaroquero + 1 Ayud.) | Jor | 0.120000 | $803.81 | $96.46 |
| Suma de Mano de Obra | $96.46 | ||||
| Costo Directo | $297.13 |