Clave | Descripción del Análisis de Precio Unitario | Unidad |
4080-20 | CIMBRA ACABADO APARENTE EN FALDONES Y PRETILES., INCLUYE: SUMINISTRO, HABILITADO, CIMBRADO Y DESCIMBRADO. | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TRIPLAY 16 MM 1 | TRIPLAY DE PINO DE 16 MM DE ESPESOR | M2 | 0.150000 | $112.00 | $16.80 |
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 5.300000 | $16.15 | $85.60 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.200000 | $34.00 | $6.80 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.190000 | $19.00 | $3.61 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 0.500000 | $2.50 | $1.25 |
Suma de Material | $119.70 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.010420 | $307.31 | $3.20 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.104170 | $251.32 | $26.18 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.104170 | $197.97 | $20.62 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.052080 | $185.16 | $9.64 |
Suma de Mano de Obra | $59.64 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $59.64 | $1.79 |
Suma de Herramienta | $1.79 | ||||
Equipo | |||||
CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.016670 | $202.91 | $3.38 |
Suma de Equipo | $3.38 | ||||
Costo Directo | $184.51 |