Clave | Descripción del Análisis de Precio Unitario | Unidad |
1001-34 | REVESTIMIENTO DE LOSA DE CONCRETO F’c=200 KG/CM2 DE 10 CM DE ESPESOR, ARMADO CON MALLA ELECTROSOLDADA 6-6/6-6 | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $24.60 | $27.06 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
CONC PREM 200 C/BOM | CONCRETO PREMEZCLADO F’c=200 KG/CM2 CON BOMBEABLE | M3 | 0.100000 | $1,168.90 | $116.89 |
Suma de Material | $145.85 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012000 | $307.31 | $3.69 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.120000 | $251.32 | $30.16 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.120000 | $197.97 | $23.76 |
Suma de Mano de Obra | $57.61 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $57.61 | $1.73 |
Suma de Herramienta | $1.73 | ||||
Equipo | |||||
VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE | HORA | 0.250000 | $42.87 | $10.72 |
Suma de Equipo | $10.72 | ||||
Costo Directo | $215.91 |