| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB-302 | GUARNICION DE CONCRETO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC 250 | CONCRETO PREMEZCLADO F´c= 250 KG/CM2 TMA 25 MM | m³ | 0.073500 | $950.00 | $69.83 |
| ACERO | VARILLA A. R. FY=4200 KG/CM2. DEL No. 3 AL 12 | kg | 2.340000 | $9.00 | $21.06 |
| ACERO ALAM | ALAMBRON DE 1/4" | KG | 1.900000 | $13.00 | $24.70 |
| PAVIMENTO-06 | MEMBRANA DE CURADO WRMEADOWS | LT | 0.180000 | $12.00 | $2.16 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.200000 | $13.80 | $2.76 |
| CELOTEX | JUNTA CONSTRUCTIVA DE CELOTEX | M2 | 0.028000 | $72.56 | $2.03 |
| Suma de Material | $122.54 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 1 OP. DE EQUIPO MENOR. | JOR | 0.100000 | $344.44 | $34.44 |
| Suma de Mano de Obra | $34.44 | ||||
| Auxiliar | |||||
| BAS -CIMMET | CIMBRA METALICA DE 40 CMS DE ALTURA | ml | 0.050000 | $356.14 | $17.81 |
| Suma de Auxiliar | $17.81 | ||||
| Costo Directo | $174.79 |