Clave | Descripción del Análisis de Precio Unitario | Unidad |
4003-09 | CIMENTACION A BASE DE ZAPATA CORRIDA DE 30 x 60 CM, FABRICACION DE CONCRETO F’c=200 KG/CM2, ARMADO CON Vs # 3 @ 18 CM INCLUYE CIMBRA Y DESCIMBRA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 12.000000 | $16.15 | $193.80 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.280000 | $34.00 | $9.52 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.120000 | $19.00 | $2.28 |
DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 4.000000 | $2.50 | $10.00 |
Suma de Material | $224.62 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012000 | $307.31 | $3.69 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.120000 | $251.32 | $30.16 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.120000 | $197.97 | $23.76 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.120000 | $185.16 | $22.22 |
Suma de Mano de Obra | $79.83 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $79.83 | $2.39 |
Suma de Herramienta | $2.39 | ||||
Auxiliar | |||||
ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 3.600000 | $23.47 | $84.49 |
CONCRETO F-C=200 1 | CONCRETO F’c=200 KG/CM2 | M3 | 0.180000 | $1,322.37 | $238.03 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.180000 | $230.70 | $41.53 |
Suma de Auxiliar | $364.05 | ||||
Costo Directo | $670.89 |