Clave | Descripción del Análisis de Precio Unitario | Unidad |
10-4430 | RECUBRIMIENTO EN MUROS CON MARMOL EN PLACA BLANCO GUADIANA DE 2 X 40 X 60 CM ASENTADO CON MORTERO CEMENTO-ARENA 1:4 INCLUYE LECHADEADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1950-20 | MARMOL LAMINADO BLANCO GUADIANA | M2 | 1.070000 | $231.28 | $247.47 |
3250-40 | TAQUETES DE PLOMO EXPANSOR DE 1″ X 1/4″ | PZA | 8.000000 | $5.43 | $43.44 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.100000 | $14.30 | $1.43 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.020000 | $18.39 | $0.37 |
Suma de Material | $292.71 | ||||
Mano de Obra | |||||
02-0650 | CUADRILLA No 65 ( 1 AZULEJERO + 1 AYUDANTE DE AZULEJERO ) | JOR | 0.222200 | $768.29 | $170.71 |
Suma de Mano de Obra | $170.71 | ||||
Auxiliar | |||||
03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 0.027000 | $927.96 | $25.05 |
Suma de Auxiliar | $25.05 | ||||
Concepto | |||||
03-0680 | LECHADA CEMENTO BLANCO-AGUA | M3 | 0.001000 | $4,645.10 | $4.65 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3º USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.111100 | $22.08 | $2.45 |
Suma de Concepto | $7.10 | ||||
Costo Directo | $495.57 |