| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C9019 | CODO DE COBRE DE 90x 19 MM. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CODO CU 90X19MM | CODO CU 90X19MM | PZA | 1.000000 | $4.28 | $4.28 |
| SOLDADURA 50X50 | SOLDADURA 50X50 | PZA | 0.020000 | $45.00 | $0.90 |
| PASTA FUNDENTE SILER | PASTA FUNDENTE SILER | PZA | 0.016670 | $38.00 | $0.63 |
| ESTOPA | Kg. | 0.041670 | $16.00 | $0.67 | |
| GAS BUTANO | GAS BUTANO | KG | 0.012750 | $7.50 | $0.10 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.022220 | $6.80 | $0.15 |
| Suma de Material | $6.73 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | jor | 0.025000 | $758.47 | $18.96 |
| Suma de Mano de Obra | $18.96 | ||||
| Costo Directo | $25.69 |