| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 06-1130 | COLUMNA EN ESTRUCTURA INCLUYE CIMBRA Y DESCIMBRA SECCION=50 X 50 CM CIMBRA COMUN REFORZADA CON 180 KG/M3 DE ACERO FY'=4200 KG/CM2 CONCRETO F'C=200 KG/CM2-3/4" | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Concepto | |||||
| 05-1150 | CIMBRA COMUN EN COLUMNAS 50 X 50 CM. | M2 | 8.000000 | $188.26 | $1,506.08 |
| 05-3230 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 Nº 5 DIAMETRO 5/8" | TON | 0.153000 | $15,178.29 | $2,322.28 |
| 05-3170 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 Nº 2 DIAMETRO 1/4" | TON | 0.027000 | $19,524.93 | $527.17 |
| 05-5730 | CONCRETO HECHO EN OBRA RESISTENCIA NORMAL VACIADO CON CARRETILLA Y BOTES F'C=200 KG/CM2 REVENIMIENTO DE 10 CM AGREGADO MAXIMO 3/4" EN COLUMNAS Y MUROS | M3 | 1.000000 | $1,482.18 | $1,482.18 |
| Suma de Concepto | $5,837.71 | ||||
| Costo Directo | $5,837.71 |