Clave | Descripción del Análisis de Precio Unitario | Unidad |
70-1310 | RASQUETEO CEPILLADO Y LIMPIEZA MANUAL DE SUPERFICIES METALICAS EN ESTRUCTURA SEMIPESADA (DE 12 A 60 KG/M) DE 0.00 A 5.00 M. DE ALTURA | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
2601-40 | THINER | LT | 0.200000 | $16.50 | $3.30 |
2601-55 | ESTOPA | KG | 0.020000 | $11.93 | $0.24 |
1652-64 | DETERGENTE EN POLVO | KG | 0.090000 | $12.21 | $1.10 |
0308-10 | TORRE DE TRABAJO DE 6 M DE ALTURA CON RUEDAS | R/D | 0.057000 | $78.33 | $4.46 |
Suma de Material | $9.10 | ||||
Mano de Obra | |||||
02-0020 | CUADRILLA No 2 ( 2 PEONES ) | JOR | 0.028500 | $573.45 | $16.34 |
Suma de Mano de Obra | $16.34 | ||||
Costo Directo | $25.44 |