| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 05-3110 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION RESISTERNCIA NORMAL FY=4200 KG/CM2 Nº 8 DIAMETRO 1" | TON |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0088-00 | VARILLA FY=4200 KG/CM2 NO. 8 ( 1" ) | TON | 1.190000 | $10,443.32 | $12,427.55 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 12.500000 | $14.30 | $178.75 |
| Suma de Material | $12,606.30 | ||||
| Mano de Obra | |||||
| 02-0620 | CUADRILLA No 62 ( 1 FIERRERO + 1 AYUDANTE DE FIERRERO ) | JOR | 3.703700 | $768.29 | $2,845.52 |
| Suma de Mano de Obra | $2,845.52 | ||||
| Costo Directo | $15,451.82 |