Clave | Descripción del Análisis de Precio Unitario | Unidad |
09-2440 | PISO DE CONCRETO ARMADO DE 10 CM DE ESPESOR CONCRETO PREMEZCLADO F’C=200 KG/CM2, AGREGADO MAXIMO 3/4″ REFUERZO = VARILLA 2.5 A/C 25 CM ACABADO ESCOBILLADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0900-08 | CONCRETO PREMEZC.RN F’C=200 KG/CM2 AGREGADO MAXIMO 3/4″ (A) | M3 | 0.104000 | $1,665.94 | $173.26 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 3.379200 | $12.58 | $42.51 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.350000 | $14.30 | $5.01 |
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,694.85 | $1.69 |
Suma de Material | $222.47 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $756.84 | $94.61 |
Suma de Mano de Obra | $94.61 | ||||
Costo Directo | $317.08 |