Clave | Descripción del Análisis de Precio Unitario | Unidad |
07-0020 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=10 X 10 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 3 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 30 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106000 | $12.74 | $14.09 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.209600 | $12.58 | $15.22 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.569200 | $12.55 | $7.14 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $14.30 | $2.86 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125000 | $18.93 | $2.37 |
0950-05 | DIESEL | LT | 0.400000 | $5.41 | $2.16 |
Suma de Material | $43.84 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.080000 | $756.84 | $60.55 |
Suma de Mano de Obra | $60.55 | ||||
Concepto | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.010500 | $981.58 | $10.31 |
Suma de Concepto | $10.31 | ||||
Costo Directo | $114.70 |