| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 04-3340 | TRAZO Y NIVELACION DE CAMPOS Y CANCHAS DEPORTIVAS DE 2 A 5 HECTAREAS | HA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 13.000000 | $12.74 | $165.62 |
| 0300-60 | CALHIDRA EN SACO | TON | 0.030000 | $1,033.57 | $31.01 |
| 1501-45 | CARRETE DE HILO DE PLASTICO PARA TRAZO CALIBRE 10 | ROL | 0.030000 | $19.47 | $0.58 |
| Suma de Material | $197.21 | ||||
| Mano de Obra | |||||
| 02-0920 | CUADRILLA No 92 ( 1 AUXILIAR DE TOPOGRAFO + 4 CADENEROS ) | JOR | 2.020000 | $1,662.81 | $3,358.88 |
| Suma de Mano de Obra | $3,358.88 | ||||
| Equipo | |||||
| 03-4280 | NIVEL PARA MEDICION K-E, TIPO DUMPY, MODELO 503 | HORA | 16.160000 | $1.07 | $17.29 |
| 03-4290 | TRANSITO PARA MEDICION K-E, MODELO CH5 | HORA | 16.160000 | $1.44 | $23.27 |
| Suma de Equipo | $40.56 | ||||
| Costo Directo | $3,596.65 |