| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 05-7160 | CONCRETO PREMEZCLADO RESISTENCIA RAPIDA VACIADO CON CARRETILLA Y BOTES F'C=350 KG/CM2 REVENIMIENTO DE 14 CM AGREGADO MAXIMO 1 1/2" EN LOSAS RETICULARES | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0900-70 | CONC. PREMEZCLADO RR F'C=350 KG/CM2 AGREGADO MAX.1 1/2" (A) | M3 | 1.040000 | $1,964.96 | $2,043.56 |
| 0901-02 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(B) | M3 | 1.040000 | $95.40 | $99.22 |
| 0601-05 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 1.040000 | $223.82 | $232.77 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.060000 | $18.39 | $1.10 |
| Suma de Material | $2,376.65 | ||||
| Mano de Obra | |||||
| 02-0450 | CUADRILLA No 45 ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.058800 | $1,881.35 | $110.62 |
| Suma de Mano de Obra | $110.62 | ||||
| Equipo | |||||
| 03-4010 | VIBRADOR DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HORA | 0.470500 | $6.55 | $3.08 |
| Suma de Equipo | $3.08 | ||||
| Costo Directo | $2,490.35 |