Clave | Descripción del Análisis de Precio Unitario | Unidad |
06-4950 | LOSA RETICULAR AUTOSUSTENTABLE FORMADA CON VIGUETA Y BOVEDILLA PERALTE = 23 CM CAPA DE COMPRESION DE 3 CM CONCRETO F’C = 200 – 3/4″ REFORZADA COM MALLA ELECTROSOLDADA 6 X 6 – 10/10 | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1300-70 | VIGUETA PRETENSA PERFIL 20, TIPO 70 M | M | 2.300000 | $181.43 | $417.29 |
1301-65 | BOVEDILLA PRETENSA 20/70 | PZA | 7.900000 | $21.84 | $172.54 |
1301-95 | MALLA ELECTROSOLDADA PRETENSA 6 X 6 10/10 | M2 | 1.100000 | $15.30 | $16.83 |
0900-08 | CONCRETO PREMEZC.RN F’C=200 KG/CM2 AGREGADO MAXIMO 3/4″ (A) | M3 | 0.040000 | $1,665.94 | $66.64 |
1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 3 1/2″ X 3 1/2″ | PT | 4.330000 | $6.25 | $27.06 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.280000 | $18.93 | $5.30 |
Suma de Material | $705.66 | ||||
Mano de Obra | |||||
02-0580 | CUADRILLA No 58 ( 1 ALBAÑIL ESPECIALIZADO + 1 AYUDANTE DE ALBAÑILERIA + 7 PEONES ) | JOR | 0.040000 | $2,821.22 | $112.85 |
Suma de Mano de Obra | $112.85 | ||||
Costo Directo | $818.51 |