Clave | Descripción del Análisis de Precio Unitario | Unidad |
18-0120 | POZO DE VISITA DE MURO DE TAB. DE 0.25 M A TIZON APL. PULIDO, DESPLANTE MAMP. ESCALONES, BROCAL Y TAPA DE FOFO. DIAM. DE 0.60 A 1.20 M SOBRE TUBO DE 0.30 A 0.45 M PROF. A RASANTE. HIDR. 3.50 M | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0302-70 | PIEDRA BRASA | M3 | 0.904700 | $260.55 | $235.72 |
3150-10 | TABIQUE COMUN DE BARRO ROJO RECOCIDO DE 5.5 X 12.5 X 25 CM | MIL | 1.638100 | $1,406.22 | $2,303.53 |
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 4.160000 | $12.74 | $53.00 |
0950-05 | DIESEL | LT | 1.880000 | $5.41 | $10.17 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.580000 | $18.93 | $10.98 |
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 11.020000 | $10.43 | $114.94 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 3.970000 | $12.55 | $49.82 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.940000 | $14.30 | $13.44 |
1550-30 | BROCAL CON TAPA 60 CM FO.FO. PESADO | PZA | 1.000000 | $2,644.43 | $2,644.43 |
1550-35 | ESCALERA DE FOFO PARA POZO DE VISITA | M | 3.000000 | $398.94 | $1,196.82 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.282000 | $18.39 | $5.19 |
Suma de Material | $6,638.04 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 8.350000 | $756.84 | $6,319.61 |
Suma de Mano de Obra | $6,319.61 | ||||
Auxiliar | |||||
03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 3.780000 | $927.96 | $3,507.69 |
Suma de Auxiliar | $3,507.69 | ||||
Concepto | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.233000 | $912.50 | $212.61 |
Suma de Concepto | $212.61 | ||||
Costo Directo | $16,677.95 |