| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 54 | SECCIÓN DE 30 X 60 CM CON 8 TUBOS DE ø 25 MM + 1 TUBOS ø 38 MM | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CR | COLORANTE ROJO 7.5 kg/m3 | kg | 1.485000 | $57.55 | $85.46 |
| TUBO ALUM. 51 MM | TUBO CONDUIT DE ALUMINIO LIBRE DE COBRE, PARED GRUESA, CUERDA ESTANDAR EN LOS EXTREMOS Y COPLES, DE 51 MM DE DIAM. | MTS | 5.500000 | $346.05 | $1,903.28 |
| TUBO ALUM. 38 MM | TUBO CONDUIT DE ALUMINIO LIBRE DE COBRE, PARED GRUESA, CUERDA ESTANDAR EN LOS EXTREMOS Y COPLES, DE 38 MM DE DIAM. | MTS | 1.100000 | $163.14 | $179.45 |
| M6X6-10/10 | MALLA ELECTROSOLDADA 6x6-10/10, ESTIRADA EN FRIO fy= 5000 kg/cm². MARCA HILSA. | m2 | 1.980000 | $43.01 | $85.16 |
| Suma de Material | $2,253.35 | ||||
| Mano de Obra | |||||
| CUAD047 | CUADRILLA AYUDANTES GENERALES | jor | 0.255000 | $536.33 | $136.76 |
| CUAD001 | CUADRILLA ELECTRICO + AYUDANTE | jor | 0.150000 | $819.83 | $122.97 |
| Suma de Mano de Obra | $259.74 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ042 | EQUIPO TARRAJA | hora | 5.040000 | $3.39 | $17.09 |
| Suma de Equipo | $17.09 | ||||
| Auxiliar | |||||
| CONC. F-C=100KG/CM2. | CONCRETO HECHO EN OBRA F'C=100 KG/CM2. AGREGADO MAXIMO DE 3/4". | M3 | 0.038500 | $950.72 | $36.60 |
| CONC. F-C=175KG/CM2. | CONCRETO HECHO EN OBRA F'C=175 KG/CM2. RESISTENCIA NORMAL, AGREGADO MAXIMO DE 3/4" | M3 | 0.192939 | $1,458.91 | $281.48 |
| VACIADO | VACIADO DE CONCRETO CON BOTES O CARRETILLA Y ACARREO HASTA 50 M. | M3 | 0.231439 | $134.17 | $31.05 |
| EXCAVACION | EXCAVACION CON EQUIPO PESADO | M3 | 0.480000 | $36.03 | $17.29 |
| ACERO CIMEN. NO. 3 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN CIMENTACION FY=4200 KG/CM2. DEL No. 3 ( 3/8" ) DE DIAM. | TON | 0.019100 | $9,192.72 | $175.58 |
| CIMBRA COMUN CIMENTA | CIMBRA COMUN DE MADERA DE PINO DE 2da. | M2 | 0.600000 | $151.18 | $90.71 |
| Suma de Auxiliar | $632.72 | ||||
| Costo Directo | $3,162.89 |