Clave | Descripción del costo horario | Unidad |
C990140-2010 | Bomba p/lanzado de concreto con motor a diesel de 35h.p. y accesorios mca. thomsen mod. p40 | hr |
DATOS GENERALES | ||||||
Vad = VALOR DE ADQUISICIÓN | $77,580.36 | Pnom = POTENCIA NOMINAL | 35.000000 | H.P. | ||
Pn = VALOR DE LAS LLANTAS | $0.00 | Fo = FACTOR DE OPERACION | 1.0000 | |||
Pa = VALOR DE PIEZAS ESPECIALES | $0.00 | TIPO DE COMBUSTIBLE | Diesel | |||
Vm = VALOR NETO | $77,580.36 | Cco = COEFICIENTE DE COMBUSTIBLE | 0.1 | |||
Vr = VALOR DE RESCATE | $15,516.07 | Pc = PRECIO DEL COMBUSTIBLE | $11.07 | /LITRO | ||
i = TASA DE INTERES | 7.500000 | /AÑO | Cc = CAPACIDAD DEL CARTER | 1.00 | LITROS | |
s = PRIMA DE SEGUROS | 2.000000 | /AÑO | Tc = TIEMPO ENTRE CAMBIO DE ACEITE | 19.047620 | HORAS | |
Ko = FACTOR DE MANTENIMIENTO | 0.200000 | HORAS | Fl = FACTOR DE LUBRICANTE | 0 | ||
Ve = VIDA ECONÓMICA | 16,800.00 | HORAS | Pac = PRECIO DEL ACEITE | $29.44 | /LITRO | |
Vn = VIDA ECONÓM. DE LAS LLANTAS | 1.00 | HORAS | Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom | 3.500000 | LITROS/HORA | |
Va = VIDA ECONOM. PIEZAS ESPECIALES | 0.00 | HORAS | Ah=CANTIDAD DE LUBRICANTE = Fl*Fo*Pnom | 0.000000 | LITROS/HORA | |
Hea = HORAS TRABAJADAS POR AÑO | 2,400.00 | HORAS | Ga=CONSUMO ENTRE CAMBIOS DE LUBRICANTE = Cc/Tc | 0.052500 | LITROS/HORA | |
CONCEPTO | OPERACIONES | ACTIVO | EN ESPERA | EN RESERVA | ||
COSTOS FIJOS | ||||||
DEPRECIACIÓN (D) = (Vm-Vr)/Ve | (77580.36-15516.07)/16800.00 | $3.69 | $2.95 | $2.95 | ||
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i | [(77580.36+15516.07)/(2*2400.00)]0.075000 | $1.45 | $1.45 | $1.45 | ||
SEGURO (Sm) = [(Vm+Vr)/2Hea]s | [(77580.36+15516.07)/(2*2400.00)]0.020000 | $0.39 | $0.39 | $0.39 | ||
MANTENIMIENTO (Mn) = Ko * D | 0.20000*3.69 | $0.74 | $0.74 | $0.59 | ||
Costos fijos | $6.27 | $5.53 | $5.38 | |||
CARGOS POR CONSUMO | ||||||
COMBUSTIBLE Co = GhxPc | 3.50000*11.07 | $38.75 | $11.63 | $0.00 | ||
OTRAS FUENTES DE ENERGÍA | 0*0 | $0.00 | $0.00 | $0.00 | ||
LUBRICANTES Lb = (Ah+Ga)Pac | (0+0.05250)29.44 | $1.55 | $0.47 | $0 | ||
LLANTAS = Pn/Vn | 0/1.00 | $0.00 | $0.00 | $0.00 | ||
PIEZAS ESPECIALES = Pa/Va | 0/0 | $0.00 | $0.00 | $0.00 | ||
Cargos por consumo | $40.30 | $12.10 | $0.00 | |||
CARGOS POR OPERACIÓN | ||||||
CATEGORÍA | CANTIDAD | SALARIO REAL | Ht | ACTIVO | EN ESPERA | EN RESERVA |
Operador equipo menor | 0.125 | $306.53 | 1.000000 | $306.53 | $0.00 | $0.00 |
Cargos por operación | ||||||
Costo Directo por Hora | $84.87 | $55.95 | $43.70 |