Clave | Descripción del costo horario | Unidad |
EQACT001 | Cortadora de concreto con disco diamantado de 12″ con motor Honda de 13 h.p. marca Target. / motor para agua de 3,500 | hr |
DATOS GENERALES | ||||||
Vad = VALOR DE ADQUISICIÓN | $18,500.00 | Pnom = POTENCIA NOMINAL | 0 | H.P. | ||
Pn = VALOR DE LAS LLANTAS | $0.00 | Fo = FACTOR DE OPERACION | 0 | |||
Pa = VALOR DE PIEZAS ESPECIALES | $140.00 | TIPO DE COMBUSTIBLE | NoUtiliza | |||
Vm = VALOR NETO | $18,360.00 | Cco = COEFICIENTE DE COMBUSTIBLE | 0 | |||
Vr = VALOR DE RESCATE | $1,836.00 | Pc = PRECIO DEL COMBUSTIBLE | $6.37 | /LITRO | ||
i = TASA DE INTERES | 8.700000 | /AÑO | ||||
s = PRIMA DE SEGUROS | 2.000000 | /AÑO | ||||
Ko = FACTOR DE MANTENIMIENTO | 0.700000 | HORAS | ||||
Ve = VIDA ECONÓMICA | 6,400.00 | HORAS | ||||
Vn = VIDA ECONÓM. DE LAS LLANTAS | 0.00 | HORAS | Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom | 1.300000 | LITROS/HORA | |
Va = VIDA ECONOM. PIEZAS ESPECIALES | 50.00 | HORAS | ||||
Hea = HORAS TRABAJADAS POR AÑO | 1,600.00 | HORAS | ||||
CONCEPTO | OPERACIONES | ACTIVO | EN ESPERA | EN RESERVA | ||
COSTOS FIJOS | ||||||
DEPRECIACIÓN (D) = (Vm-Vr)/Ve | (18360.00-1836.00)/6400.00 | $2.58 | $0.39 | $0.39 | ||
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i | [(18360.00+1836.00)/(2*1600.00)]0.087000 | $0.55 | $0.55 | $0.55 | ||
SEGURO (Sm) = [(Vm+Vr)/2Hea]s | [(18360.00+1836.00)/(2*1600.00)]0.020000 | $0.13 | $0.13 | $0.13 | ||
MANTENIMIENTO (Mn) = Ko * D | 0.700000*2.58 | $1.81 | $0.27 | $0.00 | ||
Costos fijos | $5.07 | $1.34 | $1.07 | |||
CARGOS POR CONSUMO | ||||||
1.300000*6.37 | $8.28 | $0.00 | $0.41 | |||
OTRAS FUENTES DE ENERGÍA | 0*0 | $0.00 | $0.00 | $0.00 | ||
CAPACIDAD INSTALADA Cpi = Gh/(Hea/Ma)xPc | 1.300000/(1600.000000/0)*6.37 | $0 | $0 | $0 | ||
LLANTAS = Pn/Vn | 0/0 | $0.00 | $0.00 | $0.00 | ||
PIEZAS ESPECIALES = Pa/Va | 140.00/50.00 | $2.80 | $0.00 | $0.00 | ||
Cargos por consumo | $11.81 | $0.00 | $0.45 | |||
CARGOS POR OPERACIÓN | ||||||
CATEGORÍA | CANTIDAD | SALARIO REAL | Ht | ACTIVO | EN ESPERA | EN RESERVA |
Operador cortadora de disco | 0.125 | $311.67 | 1.000000 | $311.67 | $0.00 | $0.00 |
Cargos por operación | ||||||
Costo Directo por Hora | $55.84 | $1.34 | $1.52 |