| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EST-4.7 | CONCRETO EN LOSAS, TRABES Y COLUMNAS f'c=250 Kg/cm2 PREMEZCLADO RESISTENCIA NORMAL VACIADO CON BOMBA, REVENIMIENTO DE 14 cm., TAM 3/4", INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA, MANO DE OBRA, VIBRADO, CURADO Y DEMAS CARGOS CORRESPONDIENTES ASI COMO TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0900-14 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 1.040000 | $936.00 | $973.44 |
| 0900-14 | CONCRETO PREMEZC.RR F'C=250 KG/CM2 AGREGADO MAXIMO 3/4" (A) | M3 | 1.040000 | $936.00 | $973.44 |
| 0901-00 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(A) | M3 | 1.040000 | $72.00 | $74.88 |
| 0901-00 | SOBRE PRECIO POR REV. 14 CM AGREG. 3/4" APTO PARABOMB.(A) | M3 | 1.040000 | $72.00 | $74.88 |
| 0601-05 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 1.040000 | $130.00 | $135.20 |
| 0601-05 | BOMBEO DE CONCRETO C/BOMBA EST. HASTA 5 NIVEL (15M ALTURA) | M3 | 1.040000 | $130.00 | $135.20 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.060000 | $5.00 | $0.30 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.060000 | $5.00 | $0.30 |
| Suma de Material | $2,367.64 | ||||
| Mano de Obra | |||||
| CONAGUA-45 | CUADRILLA No 45 ( 1 ALBAÑIL + 5 PEONES ) | Jor | 0.040000 | $2,422.45 | $96.90 |
| CONAGUA-45 | CUADRILLA No 45 ( 1 ALBAÑIL + 5 PEONES ) | Jor | 0.040000 | $2,422.45 | $96.90 |
| Suma de Mano de Obra | $193.80 | ||||
| Herramienta | |||||
| 00-0002 | Equipo de Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.020000 | $0.00 | $0.00 |
| 00-0002 | Equipo de Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.020000 | $0.00 | $0.00 |
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.010000 | $0.00 | $0.00 |
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.010000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CMR-03-4010 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | Hora | 0.320000 | $19.47 | $6.23 |
| CMR-03-4010 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | Hora | 0.320000 | $19.47 | $6.23 |
| Suma de Equipo | $12.46 | ||||
| Costo Directo | $2,573.90 |