| Clave | Descripci贸n del costo horario | Unidad |
| 1911-04-26 | Planta de trituraci贸n universal Pettibone 880 RH | hr |
| DATOS GENERALES | ||||||
| Vad = VALOR DE ADQUISICI脫N | $1,015,437.75 | Pnom = POTENCIA NOMINAL | 0 | H.P. | ||
| Pn = VALOR DE LAS LLANTAS | $0.00 | Fo = FACTOR DE OPERACION | 0 | |||
| Pa = VALOR DE PIEZAS ESPECIALES | $0.00 | TIPO DE COMBUSTIBLE | Electrico | |||
| Vm = VALOR NETO | $1,015,437.75 | fhk = FACTOR DE CONVERSION HP->KW | 0.746 | |||
| Vr = VALOR DE RESCATE | $203,087.55 | Pc = PRECIO DE LA ENERGIA | /KW | |||
| i = TASA DE INTERES | 16.000000 | /A脩O | ||||
| s = PRIMA DE SEGUROS | 2.000000 | /A脩O | ||||
| Ko = FACTOR DE MANTENIMIENTO | 0.700000 | HORAS | ||||
| Ve = VIDA ECON脫MICA | 14,400.00 | HORAS | ||||
| Vn = VIDA ECON脫M. DE LAS LLANTAS | 0.00 | HORAS | Gh=CANTIDAD DE ENERGIA = Fo*Pnom*fhk | 0 | KW/HORA | |
| Va = VIDA ECONOM. PIEZAS ESPECIALES | 0.00 | HORAS | ||||
| Hea = HORAS TRABAJADAS POR A脩O | 1,200.00 | HORAS | ||||
| Ht = Horas por turno | 4.260000 | Ht = HORAS | Ma = MESES POR A脩O | 0 | ||
| CONCEPTO | OPERACIONES | ACTIVO | EN ESPERA | EN RESERVA | ||
| COSTOS FIJOS | ||||||
| DEPRECIACI脫N (D) = (Vm-Vr)/Ve | (1015437.75-203087.55)/14400.00 | $56.41 | $45.13 | $45.13 | ||
| INVERSI脫N (Im) = [(Vm+Vr)/2Hea]i | [(1015437.75+203087.55)/(2*1200.00)]0.160000 | $81.24 | $81.24 | $81.24 | ||
| SEGURO (Sm) = [(Vm+Vr)/2Hea]s | [(1015437.75+203087.55)/(2*1200.00)]0.020000 | $10.15 | $10.15 | $10.15 | ||
| MANTENIMIENTO (Mn) = Ko * D | 0.700000*56.41 | $39.49 | $39.49 | $31.59 | ||
| Costos fijos | $187.29 | $176.01 | $168.11 | |||
| CARGOS POR CONSUMO | ||||||
| ENERG脥A EL脡CTRICA Co = GhxPc | 0*0 | $0.00 | $0.00 | $0.00 | ||
| OTRAS FUENTES DE ENERG脥A | 0*0 | $0.00 | $0.00 | $0.00 | ||
| CAPACIDAD INSTALADA Cpi = Gh/(Hea/Ma)xPc | 0/(1200.000000/0)*0.0 | $0 | $0 | $0 | ||
| LLANTAS = Pn/Vn | 0/0 | $0.00 | $0.00 | $0.00 | ||
| PIEZAS ESPECIALES = Pa/Va | 0/0 | $0.00 | $0.00 | $0.00 | ||
| Cargos por consumo | $0.00 | $0.00 | $0.00 | |||
| CARGOS POR OPERACI脫N | ||||||
| CATEGOR脥A | CANTIDAD | SALARIO REAL | Ht | ACTIVO | EN ESPERA | EN RESERVA |
| Operador de 1a. p/equipos menores | 1 | $471.88 | 4.260000 | $110.77 | $0.00 | $0.00 |
| Encargado de planta | 1 | $465.75 | 4.260000 | $109.33 | $0.00 | $0.00 |
| SUMA (Sr) | $937.63 | 4.260000 | $220.10 | $0 | $0 | |
| Cargos por operaci贸n (Sr/Ht) | $220.10 | $0 | $0 | |||
| CARGOS POR OTROS COSTOS | ||||||
| DESCRIPCI脫N | CANTIDAD | PRECIO UNITARIO | ACTIVO | EN ESPERA | EN RESERVA | |
| Planta con generador el茅ctrico cat 3406 | 0.4615 | $678.27 | $313.02 | 0 | 0 | |
| Cargos por otros costos | $313.02 | 0 | 0 | |||
| Costo Directo por Hora | $720.41 | $176.01 | $168.11 | |||