| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ENTOR003 | Entortado de losa de entrepiso para recibir vitropiso, a base de mortero cemento-arena 1:5, incluye: elevacion de materiales. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 06MAD001 | MADERA DE PINO | PT | 0.100000 | $10.00 | $1.00 |
| Suma de Material | $1.00 | ||||
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.130000 | $401.97 | $52.26 |
| MOA05004 | P E O N | JOR | 0.130000 | $210.17 | $27.32 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $79.58 | $3.98 |
| Suma de Mano de Obra | $83.56 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $79.58 | $1.59 |
| Suma de Herramienta | $1.59 | ||||
| Auxiliar | |||||
| BASIM005 | MEZCLA CEMENTO-ARENA 1:5 | M3 | 0.030000 | $1,128.47 | $33.85 |
| Suma de Auxiliar | $33.85 | ||||
| Costo Directo | $120.00 |