Clave | Descripción del Análisis de Precio Unitario | Unidad |
BANCA001 | Banca de concreto de 0.45 x 1.20 mts y 50 cms de altura, incluye: excavacion, dos zapatas de concreto armado de 40 x 40 cms, dos muretes de 40 x 42 cms cada uno con block 20x20x40 cms con las celdas rellenas de concreto y varillas de refuerzo de 3/8″, losa de concreto armado de 0.45 x 1.20 mts y 7 cms de espesor con cimbrado aparente y acabado pulido en la cara superior. | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01VAR003 | VARILLA CORRUGADA DE 3/8″ | KG | 13.325000 | $8.60 | $114.60 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.400000 | $18.00 | $7.20 |
06CIM005 | CIMBRAPLAY DE 5/8″ | M2 | 0.108800 | $110.00 | $11.97 |
06CLA001 | CLAVOS | KG | 0.350000 | $18.00 | $6.30 |
06MAD001 | MADERA DE PINO | PT | 3.776000 | $10.00 | $37.76 |
06TUI000 | TUINO DE MADERA | ML | 0.275000 | $4.00 | $1.10 |
13DIE000 | DIESEL | LT | 0.522000 | $7.00 | $3.65 |
19BLO020 | BLOCK DE 20x20x40 CMS CONCRETO TIPO PESADO | PZA | 4.120000 | $17.87 | $73.62 |
Suma de Material | $256.20 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.333330 | $401.97 | $133.99 |
MOF05001 | OFICIAL FIERRERO | JOR | 0.400000 | $401.97 | $160.79 |
MOC05001 | CARPINTERO DE OBRA | JOR | 0.500000 | $401.97 | $200.99 |
MOA05003 | AYUDANTE | JOR | 1.000000 | $245.43 | $245.43 |
MOA05004 | P E O N | JOR | 1.538460 | $210.17 | $323.34 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $1,064.54 | $53.23 |
Suma de Mano de Obra | $1,117.77 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $1,064.54 | $21.29 |
Suma de Herramienta | $21.29 | ||||
Equipo | |||||
MAQVI001 | VIBRADOR DE GASOLINA DE 2″ Y 8 HP | M3 | 0.109800 | $23.69 | $2.60 |
Suma de Equipo | $2.60 | ||||
Auxiliar | |||||
BASIC007 | CONCRETO F’C=200 KG/CM2, T.M.A. 3/4″ | M3 | 0.113090 | $1,272.72 | $143.93 |
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.038760 | $1,185.15 | $45.94 |
BASIC000 | CURADO CON CURACRETO | M2 | 1.098000 | $4.01 | $4.40 |
BASIM003 | MEZCLA CEMENTO-ARENA 1:3 | M3 | 0.008000 | $1,510.95 | $12.09 |
Suma de Auxiliar | $206.36 | ||||
Costo Directo | $1,604.22 |