Clave | Descripción del Análisis de Precio Unitario | Unidad |
MOLDU012 | Moldura decorativa poliestireno recubierta con malla plastica y cemen-bond, incluye: material, mano de obra y herramienta. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
26MOL000 | MOLDURA DE POLIESTIRENO | ML | 1.100000 | $53.61 | $58.97 |
01CLA002 | CLAVO PARA CONCRETO DE 2 1/2″ | PZA | 2.000000 | $2.47 | $4.94 |
26MAL000 | MALLA DE PLASTICO P/POLIESTIRENO | M2 | 1.108800 | $6.64 | $7.36 |
02CEM015 | CEMENTO PROBOND | KG | 3.000000 | $4.34 | $13.02 |
28AGUA00 | AGUA CON PIPA | M3 | 0.002000 | $80.00 | $0.16 |
Suma de Material | $84.45 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.250000 | $401.97 | $100.49 |
MOA05004 | P E O N | JOR | 0.250000 | $210.17 | $52.54 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $153.03 | $7.65 |
Suma de Mano de Obra | $160.68 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $153.03 | $3.06 |
Suma de Herramienta | $3.06 | ||||
Equipo | |||||
90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.250000 | $10.21 | $2.55 |
Suma de Equipo | $2.55 | ||||
Costo Directo | $250.74 |