| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESCAL023 | Escalon de concreto f'c= 150 kg/cm2 de medidas 0.80 x 0.30 x0.15 mts, incluye: picado de superficie, limpieza, cimbrado, colado, acabado escobillado, material y mano de obra. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 14DAR000 | DARAWELL | LT | 0.500000 | $13.79 | $6.90 |
| 06MAD001 | MADERA DE PINO | PT | 0.656170 | $10.00 | $6.56 |
| 06CIM005 | CIMBRAPLAY DE 5/8" | M2 | 0.066000 | $110.00 | $7.26 |
| 13DIE000 | DIESEL | LT | 0.060000 | $7.00 | $0.42 |
| 06CLA001 | CLAVOS | KG | 0.100000 | $18.00 | $1.80 |
| Suma de Material | $22.94 | ||||
| Mano de Obra | |||||
| MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.166670 | $401.97 | $67.00 |
| MOA05004 | P E O N | JOR | 0.166670 | $210.17 | $35.03 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $102.03 | $5.10 |
| Suma de Mano de Obra | $107.13 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $102.03 | $2.04 |
| Suma de Herramienta | $2.04 | ||||
| Auxiliar | |||||
| BASIC005 | CONCRETO F'C=150 KG/CM2, T.M.A. 3/4" | M3 | 0.037800 | $1,185.15 | $44.80 |
| Suma de Auxiliar | $44.80 | ||||
| Costo Directo | $176.91 |