Clave | Descripción del Análisis de Precio Unitario | Unidad |
MYP0033 | Plafon minaboard fisured de 0.61×1.22m. armstrong, s/p con suspension incluye: acarreos a 1a. estacion a 20 m. | m2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
A1AAR015 | Alambron 1/4″ No. 2 | t | 0.000200 | $15,000.00 | $3.00 |
PEBCA060 | Tornillo 4.2 cm 1 5/8″ cs mil | pza | 2.000000 | $0.08 | $0.16 |
A4ARA135 | Alambre galvanizado Ferretero Calibre 14.5,rollo 100 kg marca De Acero | kg | 0.120000 | $25.50 | $3.06 |
SUACA020 | Angulo perimetral 3.66 ml | pza | 0.650000 | $37.93 | $24.65 |
SUACA005 | Te principal armstrong 15/16 3.66 ml | pza | 0.900000 | $60.83 | $54.75 |
SUACA015 | Te secundaria armstrong 15/16 0.61 ml | pza | 1.700000 | $8.78 | $14.93 |
SUACA015 | Te secundaria armstrong 15/16 0.61 ml | pza | 0.900000 | $8.78 | $7.90 |
PADAG035 | Plafon fissured 755 61x122x3/4″ | pza | 1.350000 | $42.10 | $56.84 |
Suma de Material | $165.29 | ||||
Mano de Obra | |||||
JOGP026 | Cuadrilla de yeseros. Incluye : yesero, ayudante, cabo y herramienta. | jor | 0.150000 | $712.37 | $106.86 |
Suma de Mano de Obra | $106.86 | ||||
Costo Directo | $272.15 |