| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030416 | LOSA PLANA EN ESTRUCTURA, PERALTE = 20 CM CIMBRA APARENTE REFORZADA CON 120 KG DE ACERO POR M3, CONCRETO F'C = 250 - 3/4" | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Auxiliar | |||||
| 03-2080 | CONCRETO HECHO EN OBRA F'C=250 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.200000 | $782.55 | $156.51 |
| Suma de Auxiliar | $156.51 | ||||
| Concepto | |||||
| 020226 | CIMBRA APARENTE EN LOSA | M2 | 1.000000 | $123.62 | $123.62 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.012000 | $8,153.75 | $97.85 |
| Suma de Concepto | $221.47 | ||||
| Costo Directo | $377.98 |