| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 526 | 6” DIAM. (152 MM) LIMPIEZA | METROS |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CON-005A | ARENA SILICA MALLA 16/30 (TON) | TON | 0.026450 | $741.54 | $19.61 |
| PIN001 | PRIMARIO INORGANICO DE ZINC RP-4 TIPO "B" | LT | 0.064520 | $121.57 | $7.84 |
| PIN012 | ACABADO RA-26 | LT | 0.220440 | $143.89 | $31.72 |
| PIN006 | SOLVENTE 50/50 | LT | 0.003230 | $8.14 | $0.03 |
| PIN007 | SOLVENTE 80/20 | LT | 0.044090 | $11.29 | $0.50 |
| CON-006 | TRAPO DE ALGODON | KG | 0.010580 | $46.27 | $0.49 |
| MA-307 | THINNER | LT | 0.052910 | $11.96 | $0.63 |
| Suma de Material | $60.82 | ||||
| Mano de Obra | |||||
| CUAD017 | CUADRILLA SAND BLASTERO-PINTOR + AYUDANTE | jor | 0.031120 | $832.18 | $25.90 |
| Suma de Mano de Obra | $25.90 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)mo | 0.040000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| MAQ012 | EQUIPO PARA SAND BLAST Y PINTURA | hora | 0.311200 | $141.60 | $44.07 |
| Suma de Equipo | $44.07 | ||||
| Costo Directo | $130.79 |