Clave | Descripción del Análisis de Precio Unitario | Unidad |
041952 | RECUBRIMIENTO EN MUROS CON MARMOL EN PLACA VERDE IRIS DE 2 X 40 X 60 CM ASENTADO CON MORTERO CEMENTO-ARENA 1:4 INCLUYE LECHADEADO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1950-85 | MARMOL LAMINADO VERDE IRIS | M2 | 1.070000 | $607.23 | $649.74 |
3250-40 | TAQUETES DE PLOMO EXPANSOR DE 1″ X 1/4″ | PZA | 8.000000 | $3.97 | $31.76 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.100000 | $6.93 | $0.69 |
0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.020000 | $2.21 | $0.04 |
Suma de Material | $682.23 | ||||
Mano de Obra | |||||
02-0650 | CUADRILLA No 65 ( 1 AZULEJERO + 1 AYUDANTE DE AZULEJERO ) | JOR | 0.222200 | $571.57 | $127.00 |
Suma de Mano de Obra | $127.00 | ||||
Auxiliar | |||||
03-0030 | MORTERO CEMENTO-ARENA 1:4 | M3 | 0.027000 | $671.58 | $18.13 |
03-0680 | LECHADA CEMENTO BLANCO-AGUA | M3 | 0.001000 | $3,480.61 | $3.48 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.111100 | $16.06 | $1.78 |
Suma de Auxiliar | $23.39 | ||||
Costo Directo | $832.62 |