| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040636 | CASTILLO DE CONCRETO AHOGADO EN MURO DE BLOCK O TABIQUE DE PERF. VERTICAL MURO DE 12 CM (EN 3 HUECOS) CONC. F'C=150 KG/CM2-3/4" REF. CON 3 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 2 HILADAS | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8" ) | KG | 1.752000 | $4.03 | $7.06 |
| 0080-01 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | KG | 0.312000 | $4.80 | $1.50 |
| Suma de Material | $8.56 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.062500 | $564.43 | $35.28 |
| Suma de Mano de Obra | $35.28 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.021000 | $672.18 | $14.12 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.031200 | $16.06 | $0.50 |
| Suma de Auxiliar | $14.62 | ||||
| Costo Directo | $58.46 |