Clave | Descripción del Análisis de Precio Unitario | Unidad |
040182 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=30 X 15 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON ARMEX DE 15 X 30-4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 2.050000 | $14.76 | $30.26 |
0113-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 30 – 4 | M | 1.050000 | $12.54 | $13.17 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $48.10 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.117600 | $564.43 | $66.38 |
Suma de Mano de Obra | $66.38 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.047200 | $725.61 | $34.25 |
Suma de Auxiliar | $34.25 | ||||
Costo Directo | $148.73 |