Clave | Descripción del Análisis de Precio Unitario | Unidad |
040145 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=20 X 15 CM, CONCRETO F’C=150 KG/CM2-3/4″, REFORZADA CON ARMEX DE 15 X 20-4 | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.368000 | $14.76 | $20.19 |
0111-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 20 – 4 | M | 1.050000 | $10.55 | $11.08 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $35.94 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.078400 | $564.43 | $44.25 |
Suma de Mano de Obra | $44.25 | ||||
Auxiliar | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.031500 | $672.18 | $21.17 |
Suma de Auxiliar | $21.17 | ||||
Costo Directo | $101.36 |