| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040615 | CASTILLO DE CONCRETO AHOGADO EN MURO DE BLOCK O TABIQUE DE PERF. VERTICAL MURO DE 10 CM (EN 1 HUECO) CONC. F'C=150 KG/CM2-3/4" REF. CON 1 VARILLA A.R. DE 5/16" ESTRIBOS DE 1/4" A/C 2 HILADAS | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16") | KG | 0.410000 | $8.32 | $3.41 |
| Suma de Material | $3.41 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.033300 | $564.43 | $18.80 |
| Suma de Mano de Obra | $18.80 | ||||
| Auxiliar | |||||
| 03-2040 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.005200 | $672.18 | $3.50 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.016700 | $16.06 | $0.27 |
| Suma de Auxiliar | $3.77 | ||||
| Costo Directo | $25.98 |