| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 010718 | PLANTILLA DE PEDACERIA DE TABIQUE EN 15 CM. CON MORTERO HIDRAULICO-ARENA 1:5 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0303-30 | PEDACERIA DE TABIQUE | M3 | 0.189700 | $72.80 | $13.81 |
| Suma de Material | $13.81 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.071400 | $564.43 | $40.30 |
| Suma de Mano de Obra | $40.30 | ||||
| Auxiliar | |||||
| 03-0110 | MEZCLA MORTERO HIDRAULICO-ARENA 1:5 | M3 | 0.049500 | $364.39 | $18.04 |
| Suma de Auxiliar | $18.04 | ||||
| Costo Directo | $72.15 |