| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CONCRETO MR-45 | CONCRETO EN RAMPA MR-45 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO MR-45 24 | Concreto premezclado MR=45 a 24 horas | M3 | 1.100000 | $1,411.25 | $1,552.38 |
| PAVIMENTO-06 | CURACRETO ANTISOL MARCA SIKA | LT | 1.500000 | $23.00 | $34.50 |
| ACMXX005 | Agua | m3 | 0.050000 | $40.00 | $2.00 |
| FEXPAN | fexpan | m2 | 1.000000 | $279.00 | $279.00 |
| MALLA | Malla soldada 66-44, marca De Acero | m2 | 1.100000 | $40.00 | $44.00 |
| Suma de Material | $1,911.88 | ||||
| Mano de Obra | |||||
| 02CALB2 | (1 Albañil + 3 Ayudantes) | Jor | 0.127970 | $1,702.27 | $217.84 |
| Suma de Mano de Obra | $217.84 | ||||
| Equipo | |||||
| VIBRADOR2 | VIBRADOR CONCRETO MCA. CIPSA MOD. MVK4 CON MOTOR A 4 HP CON CONJUNTO CABEZAL 4 MT | HR | 0.269540 | $62.07 | $16.73 |
| Suma de Equipo | $16.73 | ||||
| Otros | |||||
| AUX-15 | CIMBRA COMUN DE MADERA INCLUYE: SUMINISTRO DE MATERIALES, HABILITADO, SEPRADORES, LUBRICANTES, DESCIMBRADO, EQUIPO, HERRAMIENTA, MANO DE OBRA, RAHABILITADO, PARA SU REUSO, (CINCO USOS) Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION. | M2 | 0.200000 | $144.71 | $28.94 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 12.000000 | $16.14 | $193.68 |
| Suma de Otros | $222.62 | ||||
| Costo Directo | $2,369.07 |