Clave | Descripción del Análisis de Precio Unitario | Unidad |
041430 | PISO DE CONCRETO ARMADO DE 10 CM DE ESPESOR CONCRETO HECHO EN OBRA F’C=100 KG/CM2, AGREGADO MAXIMO 1 1/2″ REFUERZO = MALLA 66-1010 ACABADO PULIDO | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
0107-00 | MALLA ELECTROSOLDADA TECNOMALLA 6 X 6-10/10 | M2 | 1.020000 | $5.46 | $5.57 |
0300-03 | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.001000 | $1,298.69 | $1.30 |
Suma de Material | $6.87 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.125000 | $564.43 | $70.55 |
Suma de Mano de Obra | $70.55 | ||||
Auxiliar | |||||
03-2150 | CONCRETO HECHO EN OBRA F’C=100 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2″ | M3 | 0.104000 | $586.61 | $61.01 |
Suma de Auxiliar | $61.01 | ||||
Costo Directo | $138.43 |