| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| EX-VIG-8.16 | CIMBRADO Y DESCIMBRADO EN CIMENTACION. INCLUYE : MATERIALES, MANO DE OBRA Y HERRAMIENTA NECESARIOS PARA SU CORRECTA EJECUCIÓN. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.000000 | $14.18 | $14.18 |
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 0.139640 | $14.18 | $1.98 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 1.000000 | $14.18 | $14.18 |
| 0122-00 | SEPARADOR METALICO DE 5/16 CON TUERCA | PZA | 0.030000 | $15.00 | $0.45 |
| 0085-00 | VARILLA FY=4200 KG/CM2 NO. 4 ( 1/2" ) | KG | 0.100000 | $12.30 | $1.23 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.200000 | $16.25 | $3.25 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.150000 | $15.63 | $2.34 |
| 0950-05 | DIESEL | LT | 0.500000 | $9.92 | $4.96 |
| 1900-80 | TRIPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.057400 | $250.00 | $14.35 |
| Suma de Material | $56.92 | ||||
| Mano de Obra | |||||
| CONAGUA-59 | CUADRILLA No 59 ( 1 CARPINTERO DE OBRA NEGRA + 1 AYUDANTE DE CARPINTERIA OBRA NEGRA ) | Jor | 0.090000 | $942.00 | $84.78 |
| Suma de Mano de Obra | $84.78 | ||||
| Herramienta | |||||
| 00-0001 | HERRAMIENTA MENOR | (%)mo | 0.020000 | $84.78 | $1.70 |
| 00-0002 | Equipo de Seguridad (Casco, Botas, Guantes, Gafas, Chaleco Preventivo) | (%)mo | 0.040000 | $84.78 | $3.39 |
| Suma de Herramienta | $5.09 | ||||
| Otros | |||||
| PRETRZ-001 | TRAZO Y NIVELACION A MANO, INCLUYE :MATERIALES, EQUIPO, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION | M2 | 0.050000 | $8.70 | $0.44 |
| Suma de Otros | $0.44 | ||||
| Costo Directo | $147.23 |