Clave | Descripción del Análisis de Precio Unitario | Unidad |
040493 | CASTILLO DE CONCRETO SECCION= 15 X 20 CM, CONCRETO F’C=150 KG/CM2-3/4″, CIMBRA 2 CARAS, REFORZADO CON 4 VARILLAS R.N. DE 3/8″ ESTRIBOS DE 1/4″ A/C 25 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.196000 | $14.76 | $17.65 |
0084-00 | VARILLA FY=4200 KG/CM2 NO. 3 ( 3/8″ ) | KG | 2.339400 | $4.03 | $9.43 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.843300 | $4.80 | $4.05 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.200000 | $6.93 | $1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.135000 | $5.48 | $0.74 |
0950-05 | DIESEL | LT | 0.600000 | $4.24 | $2.54 |
Suma de Material | $35.80 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.114200 | $564.43 | $64.46 |
Suma de Mano de Obra | $64.46 | ||||
Auxiliar | |||||
03-2040 | CONCRETO HECHO EN OBRA F’C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.031500 | $672.18 | $21.17 |
03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.114200 | $16.06 | $1.83 |
Suma de Auxiliar | $23.00 | ||||
Costo Directo | $123.26 |