| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 070327 | SUMINISTRO Y COLOCACION DE CRUZ DE BRONCE PARA CONEXION DE COBRE DE 19 MM | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 3007-34 | CRUZ DE BRONCE PARA CONEXION DE COBRE DE 19 MM | PZA | 1.030000 | $38.65 | $39.81 |
| 3035-30 | SOLDADURA 50 X 50 EN CARRETE DE 0.200 KGS | CARR | 0.035600 | $29.88 | $1.06 |
| 3035-16 | PASTA PARA SOLDAR EN BOTE DE 75 GRAMOS | KG | 0.007200 | $52.30 | $0.38 |
| 3037-34 | GASOLINA BLANCA | LT | 0.170000 | $7.82 | $1.33 |
| 1502-70 | SEGUETA DE ACERO | PZA | 0.084000 | $6.70 | $0.56 |
| 3035-68 | LIJA PARA PLOMERIA DE 25 MM | M | 0.062000 | $4.08 | $0.25 |
| Suma de Material | $43.39 | ||||
| Mano de Obra | |||||
| 02-0820 | CUADRILLA No 82 ( 1 PLOMERO + 1 AYUDANTE DE PLOMERO ) | JOR | 0.125000 | $628.87 | $78.61 |
| Suma de Mano de Obra | $78.61 | ||||
| Costo Directo | $122.00 |