| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4030 05 | De f'c=250 kg/cm2. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| CURAFEST | MEMBRANA DE CURADO COLOR BLANCO FESTER | LTO | 0.220000 | $31.83 | $7.00 |
| AGUA-01 | AGUA (ADQUIRIDA EN PIPA) | m3 | 0.150000 | $75.79 | $11.37 |
| Suma de Material | $18.37 | ||||
| Equipo | |||||
| MAQUI-09 | VIBRADOR DE CHICOTE DYNPAC 4 HP A GASOLINA. | hora | 0.500000 | $9.98 | $4.99 |
| Suma de Equipo | $4.99 | ||||
| Auxiliar | |||||
| CONCRETO-250 | CONCRETO HIDRAULICO F'c= 250 KG/CM2 | M3 | 1.050000 | $1,075.98 | $1,129.78 |
| CUAD-002 | CUADRILLA No.2 1 OF. ALBAÑIL + 1 AYTE. | jor | 0.350000 | $657.83 | $230.24 |
| Suma de Auxiliar | $1,360.02 | ||||
| Costo Directo | $1,383.38 |