| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 100 NIVEL-05 | CASTILLOS K3 4 VARILLAS DEL No. 4 ESTRIBOS DE 1/4" A/C 20 CMS 12*30 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA ACARREO INTERNO | M3 | 0.060000 | $40.00 | $2.40 |
| Suma de Material | $2.40 | ||||
| Mano de Obra | |||||
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.071429 | $642.91 | $45.92 |
| Suma de Mano de Obra | $45.92 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF | ACERO DE REFUERZO VARIOS DIAMETROS | TON | 0.003980 | $14,909.35 | $59.34 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 1.560000 | $14.89 | $23.23 |
| CE-02-01 | CIMBRA COMUN | M2 | 0.600000 | $170.37 | $102.22 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.036000 | $903.30 | $32.52 |
| Suma de Auxiliar | $217.31 | ||||
| Costo Directo | $265.63 |