Clave | Descripción del Análisis de Precio Unitario | Unidad |
IB17BL | Te de cobre a cobre de 102 mm ( 4″ ) de diámetro. | pieza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
DCK21 | Te de 102 mm (4 ”) cobre a cobre a cobre int. Fig 711. | pieza | 1.010000 | $487.36 | $492.23 |
A5LT1 | Lija 25 mm (1″) x 1.00 m. | m | 0.210000 | $3.09 | $0.65 |
A7LEZ | Pasta fundente. | kg | 0.011050 | $48.00 | $0.53 |
A1AB1 | Gasolina Magna. | lto | 0.300000 | $4.27 | $1.28 |
A7LEB | Soldadura 50-50 carrete. | kg | 0.088440 | $65.70 | $5.81 |
Suma de Material | $500.50 | ||||
Mano de Obra | |||||
F09 | Plomero | Turno | 0.083330 | $159.16 | $13.26 |
B11 | Ayudante de plomero | Turno | 0.083330 | $94.01 | $7.83 |
J02 | Cabo | Turno | 0.008330 | $164.32 | $1.37 |
Suma de Mano de Obra | $22.46 | ||||
Herramienta | |||||
03 | Herramienta | (%)mo | 0.030000 | $22.46 | $0.67 |
Suma de Herramienta | $0.67 | ||||
Costo Directo | $523.63 |