Clave | Descripción del Análisis de Precio Unitario | Unidad |
GH13BD | Piso de concreto R.N. f’c= 150 kg/cm2 de 8 cm de espesor. | m2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
A1A3A | Cemento gris | ton | 0.001000 | $1,182.61 | $1.18 |
Suma de Material | $1.18 | ||||
Mano de Obra | |||||
F02 | Mosaiquero | Turno | 0.058820 | $154.08 | $9.06 |
B02 | Ayudante de mosaiquero | Turno | 0.058820 | $94.01 | $5.53 |
J02 | Cabo | Turno | 0.005880 | $164.32 | $0.97 |
Suma de Mano de Obra | $15.56 | ||||
Herramienta | |||||
09 | Herramienta menor. | (%)mo | 0.030000 | $15.56 | $0.47 |
Suma de Herramienta | $0.47 | ||||
Concepto | |||||
F5*1B2 | Concreto F’c = 150 kg/cm2, T.M.A. de 40 mm, resistencia normal. | m3 | 0.084000 | $499.44 | $41.95 |
Suma de Concepto | $41.95 | ||||
Costo Directo | $59.16 |