| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GC22FB | Muro de 14 cm de espesor aparente dos caras, colores rojo, ocre o blanco. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| A1CB5 | Tabique perforado vertical 10 x 14 x 20 cm natural Sta. Julia. | 100 | 0.489000 | $880.00 | $430.32 |
| A7B32 | Varilla de refuerzo 7.9 mm ( 5/16") diámetro. | kg | 0.470000 | $3.83 | $1.80 |
| Suma de Material | $432.12 | ||||
| Mano de Obra | |||||
| E01 | Oficial albañil | Turno | 0.133330 | $143.81 | $19.17 |
| B23 | Ayudante | Turno | 0.133330 | $94.01 | $12.53 |
| J02 | Cabo | Turno | 0.013330 | $164.32 | $2.19 |
| Suma de Mano de Obra | $33.89 | ||||
| Herramienta | |||||
| 16 | Elevación | (%)mo | 0.020000 | $33.89 | $0.68 |
| 09 | Herramienta menor. | (%)mo | 0.020000 | $33.89 | $0.68 |
| 30 | Andamios. | (%)mo | 0.040000 | $33.89 | $1.36 |
| Suma de Herramienta | $2.72 | ||||
| Concepto | |||||
| F2*A02 | Mortero cemento-arena 1:4. | m3 | 0.017000 | $578.56 | $9.84 |
| F5*1B1 | Concreto F'c = 150 kg/cm2, T.M.A. de 20 mm, resistencia normal. | m3 | 0.008400 | $536.11 | $4.50 |
| Suma de Concepto | $14.34 | ||||
| Costo Directo | $483.07 |