| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| SE13CC | Renivelaci贸n de brocales de fierro fundido. | pieza |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| A1BA1 | Tabique rojo recocido. | mil | 0.024000 | $934.78 | $22.43 |
| Suma de Material | $22.43 | ||||
| Mano de Obra | |||||
| E01 | Oficial alba帽il | Turno | 0.143000 | $143.81 | $20.56 |
| B23 | Ayudante | Turno | 0.286000 | $94.01 | $26.89 |
| J02 | Cabo | Turno | 0.014300 | $164.32 | $2.35 |
| Suma de Mano de Obra | $49.80 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.030000 | $49.80 | $1.49 |
| Suma de Herramienta | $1.49 | ||||
| Concepto | |||||
| F2*A01 | Mortero cemento-arena 1:3. | m3 | 0.020000 | $693.24 | $13.86 |
| Suma de Concepto | $13.86 | ||||
| Costo Directo | $87.58 |