Clave | Descripción del auxiliar o básico | Unidad |
BASIP092 | CALZA DE CONCRETO (POLLO) PARA ACERO SUPERIOR | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.03 | 18 | 0.54 |
06MAD001 | MADERA DE PINO | PT | 0.004 | 10 | 0.04 |
06CLA001 | CLAVOS | KG | 0.01 | 18 | 0.18 |
13DIE000 | DIESEL | LT | 0.01 | 7 | 0.07 |
Suma de Material | 0.83 | ||||
Mano de Obra | |||||
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.005 | 401.97 | 2.01 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.05 | 2.01 | 0.1 |
Suma de Mano de Obra | 2.11 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.02 | 2.01 | 0.04 |
Suma de Herramienta | 0.04 | ||||
Auxiliar | |||||
BASIC007 | CONCRETO F’C=200 KG/CM2, T.M.A. 3/4″ | M3 | 0.00022 | 1272.72 | 0.28 |
Suma de Auxiliar | 0.28 | ||||
Costo Directo | 3.26 |