Clave | Descripción del auxiliar o básico | Unidad |
040118 | DALA O CADENA DE DESPLANTE, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 15 CM, CONCRETO F’C=200 KG/CM2-3/4″, REFORZADA CON 4 VARILLAS A.R. DE 5/16″ ESTRIBOS DE 1/4″ A/C 30 CM | M |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1″ X 4″ | PT | 1.106 | 14.76 | 16.32 |
0091-01 | VARILLA ALTA RESISTENCIA FY=6000 NO 2.5 (5/16″) | KG | 1.1628 | 8.32 | 9.67 |
0080-01 | ALAMBRON LISO DE 1/4″ ( NO. 2 ) | KG | 0.7379 | 4.8 | 3.54 |
0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.2 | 6.93 | 1.39 |
0100-00 | CLAVO DE 2 1/2″ A 3 1/2″ | KG | 0.125 | 5.48 | 0.69 |
0950-05 | DIESEL | LT | 0.4 | 4.24 | 1.7 |
Suma de Material | 33.31 | ||||
Mano de Obra | |||||
02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.0851 | 564.43 | 48.03 |
Suma de Mano de Obra | 48.03 | ||||
Auxiliar | |||||
03-2060 | CONCRETO HECHO EN OBRA F’C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4″ | M3 | 0.0236 | 725.61 | 17.12 |
Suma de Auxiliar | 17.12 | ||||
Costo Directo | 98.46 |